WEEKS 18-19 WMRA CONSTRUCTION SITE
WEEKS 18-19: December 7 – December 19 BUILDING Continue with steel stud walls and sheeting Install roof drains Begin installation of membrane roof Begin work on brick and window frames
View ArticleWEEKS 20-21 WMRA CONSTRUCTION SITE
WEEKS 20-21: December 21 – January 2, 2016 BUILDING Finished exterior walls Continue interior steel stud walls and sheeting Installed roof penetration Began installation of membrane roof Began window...
View ArticleWEEKS 22-23 WMRA CONSTRUCTION SITE
WEEKS 22-23: January 4-16, 2016 BUILDING Completed exterior and interior steel stud installation Completed sheeting Completed roofing for upper roof Continued roofing for lower roof Continued...
View ArticleWEEKS 24-25 WMRA CONSTRUCTION SITE
WEEKS 24-25: January 18-25, 2016 BUILDING Completed roof Completed roof drains Poured concrete for fireplace wall Finished plumbing and electrical rough in Continued installation of window frames and...
View ArticleWEEKS 26-27 WMRA CONSTRUCTION SITE
WEEKS 26-27: February 1-13, 2016 BUILDING Completed roofing North and east windows installed Completed plumbing and electrical rough-in Semco installed gas service BPW installed power to building...
View ArticleCommittee Tours New Business Center
The WMAA Building & Development Committee toured the new Airport Business Center. Committee members were excited to see the progress made. To date the roofing has been completed including the...
View ArticleWEEKS 28-29 WMRA CONSTRUCTION SITE
WEEKS 28-29: February 15-27, 2016 BUILDING Completed insulation and steel framing Installed permanent power Installed fireplace Began gypsum board and drywall installation and masonry Continued...
View ArticleENERGY SAVING WINDOWS BEING INSTALLED AT WMRA
Pleotint, whose corporate headquarters and manufacturing are located in Jension, is all about saving energy. The low-e glass which allows visible light to pass through while controlling the passage...
View Article2016 WINGS OF MERCY CAREAFFAIRE
Please join us on Saturday, August 20, 8:00 a.m. – 12 noon for the 2016 Holland Wings of Mercy CareAffaire at West Michigan Regional Airport. To register for the Wings of Mercy Runway 5K, use the...
View ArticleWEEKS 30-31 WMRA CONSTRUCTION SITE
WEEKS 30-31: February 29 – March 12 BUILDING Continue drywall installation Continue masonry Continue HVAC and electrical Install Suntuitive Glass Continue electrical work Installed fireplace
View ArticleWEEKS 32-33 WMRA CONSTRUCTION SITE
WEEKS 30-31: March 14 – March 26 BUILDING Continued HVAC and electrical Continued drywall finishing Continued priming/painting Continued framing wood ceiling panels SITE IMPROVEMENTS Continued fine...
View ArticleWEEKS 34-35 WMRA CONSTRUCTION SITE
WEEKS 34-35: March 28 – April 9 BUILDING Continue HVAC, electrical work, plumbing Start bathroom tile Masonry work Continue framing ceiling and installing ceiling grid Installed bathroom cabinets and...
View ArticleWEEKS 36-37 WMRA CONSTRUCTION SITE
WEEKS 36-37: April 11 – April 23 BUILDING Continued HVAC, electrical and plumbing Began siding Began acoustic ceiling grid Continue metal siding Finish tile SITE Installed sub-base for cul-de-sac...
View ArticleWEEKS 38-39 WMRA CONSTRUCTION SITE
WEEKS 38-39: April 25 – May 7 BUILDING Began window flashing Continued HVAC, electrical and plumbing Continued metal siding Continued cabinet installation Continued painting Completed acoustical...
View ArticleJET FLOAT IN TULIP TIME MUZIEKPARADE
The cold and wind didn’t stop the crowds from coming to watch the 2016 Tulip Time Muziekparade. Thousands of people lined the streets to get a view of the marching bands, floats and all the parade...
View ArticleWEEKS 40-41 WMRA CONSTRUCTION SITE
WEEKS 40-41: May 9 – 21 BUILDING Continued HVAC, electrical and plumbing Continued metal siding Continued installing cabinets Completed window flashing Installed bathroom fixtures Installed acoustic...
View ArticleCONGRATULATIONS TO ERIC
Congratulations to Eric Sutherland (pictured on the right) who just finished his flight training and check ride with flight instructor Derek Stewart, Tulip City Air, at West Michigan Regional Airport....
View ArticleWEEKS 42-43 WMRA CONSTRUCTION SITE
WEEKS 42-43: May 23 – June 4 BUILDING Continued HVAC, electrical and plumbing Began fin tube cabinets Installed carpet Complete painting Continued installing cabinets Complete metal siding Installed...
View ArticleWEEKS 44-45 WMRA CONSTRUCTION SITE
WEEKS 44-45: June 6 – June 18 BUILDING Continued HVAC, electrical and plumbing Complete cabinets Complete installation of carpet Complete epoxy floor Complete painting Begin floor mats Install ramp...
View ArticleWEEKS 46-49 WMRA CONSTRUCTION SITE
WEEKS 46-49: June 20 – July 16 BUILDING & SITE Continue small building and site projects Waiting for furniture