WEEKS 18-19: December 7 – December 19
BUILDING
Continue with steel stud walls and sheeting
Install roof drains
Begin installation of membrane roof
Begin work on brick and window frames
↧
WEEKS 18-19 WMRA CONSTRUCTION SITE
↧