WEEKS 20-21 WMRA CONSTRUCTION SITE

$
0
0

x IMG_1755WEEKS 20-21:  December 21 – January 2, 2016
BUILDING
Finished exterior walls
Continue interior steel stud walls and sheeting
Installed roof penetration
Began installation of membrane roof
Began window frame installation
Began mechanical, plumbing and electrical rough-in

 