WEEKS 20-21 WMRA CONSTRUCTION SITE

Image may be NSFW.
Clik here to view.
x IMG_1755
WEEKS 20-21:  December 21 – January 2, 2016
BUILDING
Finished exterior walls
Continue interior steel stud walls and sheeting
Installed roof penetration
Began installation of membrane roof
Began window frame installation
Began mechanical, plumbing and electrical rough-in

 