WEEKS 24-25: January 18-25, 2016
BUILDING
Completed roof
Completed roof drains
Poured concrete for fireplace wall
Finished plumbing and electrical rough in
Continued installation of window frames and windows
Begin HVAC and installation of glass
Install cable from transformer pad to building
↧
WEEKS 24-25 WMRA CONSTRUCTION SITE
↧