Clik here to view.WEEKS 26-27: February 1-13, 2016
BUILDING
Completed roofing
North and east windows installed
Completed plumbing and electrical rough-in
Semco installed gas service
BPW installed power to building
Completed steel stud walls
Begin exterior wall insulation