WEEKS 38-39 WMRA CONSTRUCTION SITE

$
0
0

3 weeks 38-39 050616WEEKS 38-39: April 25 – May 7
BUILDING
Began window flashing
Continued HVAC, electrical and plumbing
Continued metal siding
Continued cabinet installation
Continued painting
Completed acoustical ceiling grid
Completed ceiling clouds
Installed snowmelt in north sidewalk

SITE
Poured curb and gutter for cul-de-sac
Continued topsoiling
Sidewalk prep work
Concrete apron paving